Violation Detail
Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1714877.015
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,131.00
Current Penalty: $16,131.00
Issuance Date: 04/17/2024
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/04/2024
Gravity: 10
Report ID: 0626000
Contest Date: 05/13/2024
Final Order:
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 05/13/2024 | $16,131.00 | 06/04/2024 | Serious | |
Penalty | Z: Issued | 04/17/2024 | $16,131.00 | 06/04/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures were not developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section. On or about December 2, 2023, and at times prior thereto employees conducted repair operations for the Auxiliary "A" transformer cooling system, and the employer did not develop, and document procedures to control hazardous energy.