Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1712170.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $14,000.00
Issuance Date: 05/20/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 05/24/2024
Gravity: 10
Report ID: 0215000
Contest Date: 06/12/2024
Final Order: 05/23/2025
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/23/2025 | $14,000.00 | 05/24/2024 | Serious | |
Penalty | C: Contested | 06/13/2024 | $16,131.00 | 05/24/2024 | Serious | |
Penalty | Z: Issued | 05/20/2024 | $16,131.00 | 05/24/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.416(a)(3): Before work began the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring a person, tool, or machine into physical or electrical contact with the energized electric power circuit: Location: 175 Water St. New York, NY; 23rd floor On or about 11/21/2023, a) The employer did not ensure the work area behind the ceiling was free of energized electrical power circuit. Employees were installing lights in the ceiling where lock out tag out was not completed. An employee came in contact with an energized circuit.