Violation Detail
Standard Cited: 19260251 A01 Rigging equipment for material handling.
Inspection Nr: 1701370.015
Citation: 01002
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $11,292.00
Current Penalty: $5,650.00
Issuance Date: 02/26/2024
Nr Instances: 1
Nr Exposed: 12
Abatement Date: 03/03/2025
Gravity: 10
Report ID: 0522500
Contest Date: 03/22/2024
Final Order: 02/21/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 02/21/2025 | $5,650.00 | 03/03/2025 | Serious | |
| Penalty | C: Contested | 03/27/2024 | $11,292.00 | 03/07/2024 | Serious | |
| Penalty | Z: Issued | 02/26/2024 | $11,292.00 | 03/07/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.251(a)(1): Rigging equipment for material handling was not inspected prior to use on each shift and as necessary during its use to ensure that it was safe. Defective rigging equipment was not removed from service: a. Mingo's Construction LLC located at 860 Jaeger Street, Columbus, OH 43206: On or about October 4, 2023, during the construction of a mixed-use (commercial/residential) building, the employer did not ensure that rigging equipment for material handling was inspected prior to use on each shift and as necessary during its use to ensure that it was safe and free of defects. The following condition exposed employees to struck-by hazards.
Translate