Standard Cited: 19260403 H General requirements.
Inspection Nr: 1697240.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,358.00
Current Penalty: $1,200.00
Issuance Date: 11/27/2023
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 12/11/2023
Gravity: 5
Report ID: 0625700
Contest Date:
Final Order: 02/05/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/05/2024 | $1,200.00 | 12/11/2023 | Serious | |
| Penalty | Z: Issued | 11/27/2023 | $5,358.00 | 12/11/2023 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.403(h): Each service, feeder, and branch circuit was not legibly marked at its disconnecting means or overcurrent device to indicate its purpose, nor located and arranged so that the purpose was evident. On or about September 13, 2023, the employees conducted construction work using electrical power supply panels that were not legibly marked to indicate their purpose.