Violation Detail
Standard Cited: 19100269 L02 I B Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1693573.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,938.00
Current Penalty: $8,204.00
Issuance Date: 01/19/2024
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/03/2024
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 02/16/2024
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/16/2024 | $8,204.00 | 06/03/2024 | Serious | |
| Penalty | Z: Issued | 01/19/2024 | $10,938.00 | 01/29/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(l)(2)(i)(B): At least two employees were not present for the installation, removal, or repair of deenergized lines where an employee is exposed to contact with other parts energized at more than 600 volts: (a) On or about August 24th, 2023, for an employee who suffered electrocution while working alone to repair an outage on a 7,200 volt power line at or near, 29552 State Highway 35, Prairie Du Chien, WI 53821.
Translate