Violation Detail
Standard Cited: 19260950 D01 General.
Inspection Nr: 1690078.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $16,131.00
Issuance Date: 02/05/2024
Nr Instances: 1
Nr Exposed: 9
Abatement Date: 03/01/2024
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 02/28/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/28/2024 | $16,131.00 | 03/01/2024 | Other | |
| Penalty | Z: Issued | 02/05/2024 | $16,131.00 | 03/01/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.950(d)(1): The nominal voltages of lines and equipment was not determined before work on or near the lines or equipment was started: a) On or about August 9, 2023, the nominal voltages of overhead powerlines was not determined prior to operating an excavator beneath the lines, exposing employees to electrical hazards.