Violation Detail
Standard Cited: 19260451 F07 General requirements.
Inspection Nr: 1675615.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $5,156.00
Current Penalty: $2,000.00
Issuance Date: 06/16/2023
Nr Instances: 2
Nr Exposed: 2
Abatement Date:
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order: 07/21/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/21/2023 | $2,000.00 | Serious | ||
| Penalty | Z: Issued | 06/16/2023 | $5,156.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person. Location: 6 Pelissier Circle Randolph, MA On June 8th, 2023, employees were exposed to falls from heights up to 14 feet to the ground while working from a carpenters' bracket scaffold system and a hand built bracket scaffold system on a wood framing project where a competent person qualified in scaffold erection was not present to supervise or direct the scaffold erection. Instances: 1) Carpenters Bracket Scaffold 2) Hand Built Bracket Scaffold