Violation Detail
Standard Cited: 19100217 E01 Mechanical power presses.
Inspection Nr: 1655170.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,641.00
Current Penalty: $4,980.75
Issuance Date: 04/27/2023
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 05/19/2023
Gravity: 5
Report ID: 0213600
Contest Date:
Final Order: 05/16/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/16/2023 | $4,980.75 | 05/19/2023 | Serious | |
| Penalty | Z: Issued | 04/27/2023 | $6,641.00 | 05/19/2023 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.217(e)(1): The employer did not establish and follow an inspection program having a general component and a directed component. a) On or about 03/08/2023, in the press area, a mechanical power press inspection program having a general and directed component that consists of periodic and regular inspections of auxiliary equipment, safeguards, clutch/brake mechanism, anti-repeat feature, single-stroke mechanism, and its parts was not establish to assure presses, such as but not limited to, Press # 872, # 892, # 317, # 1008, are in a safe operating condition. ABATEMENT CERTIFICATION REQUIRED