Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1595879.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $14,502.00
Current Penalty: $7,251.00
Issuance Date: 05/23/2022
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 06/17/2022
Gravity: 10
Report ID: 0420600
Contest Date: 06/24/2022
Final Order: 01/04/2023
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/04/2023 | $7,251.00 | 06/17/2022 | Serious | |
| Penalty | C: Contested | 07/12/2022 | $14,502.00 | 06/17/2022 | Serious | |
| Penalty | Z: Issued | 05/23/2022 | $14,502.00 | 06/17/2022 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to Items of this section: a. On or about May 13, 2022, at the facility, employees were changing-out rotary die cutting boards on a rotary die cutter machine, during which time the energy control procedure (Intermediate Energy State/ IES procedure) did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy; therefore, exposing the employees to amputation hazards. b. On or about May 13, 2022, at the facility, employees were conducting weekly Preventative Maintenance/ PM, such as weekly cleaning of the rotary die cutter machine, during which time the energy control procedure (Zero Energy State/ ZES procedure) did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy; therefore, exposing the employees to amputation hazards.