Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 1592816.015
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $10,360.00
Current Penalty: $0.00
Issuance Date: 10/20/2022
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 11/16/2022
Gravity: 5
Report ID: 0728500
Contest Date: 11/15/2022
Final Order: 03/13/2023
Related Event Code (REC):
Emphasis:
Substance: 0170
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/13/2023 | $0.00 | 11/16/2022 | Serious | |
Penalty | C: Contested | 11/17/2022 | $10,360.00 | 11/16/2022 | Serious | |
Penalty | Z: Issued | 10/20/2022 | $10,360.00 | 11/16/2022 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.119(d)(3)(ii): The employer did not document that the equipment complies with recognized and generally accepted good engineering practices. At a worksite located at 4600 Waco Rd, Columbia, MO 65202 (Ammonia Yard): The employer failed to protect employees because the employer did not document that the equipment complies with the employer's chosen recognized and generally accepted good engineering practices (RAGAGEP). This was last demonstrated on or about September 28, 2022, and at times prior to that. a) This included but was not limited to ANSI/IIAR 2 - 2021 Section 5.14.6, when the ammonia piping system line B3 PHL HDP located in Powerhouse Yard on P&ID R706 was not labeled with the following information: "ammonia, physical state (e.g. liquid or gas), relative pressure level, and direction of flow. b) This included but was not limited to ANSI/IIAR 2 - 2021 Section 5.14.6, when the ammonia piping system line N HPR associated with HV2 located in Powerhouse Yard on P&ID R 706 was not labeled with the following information: "ammonia, physical state (e.g. liquid or gas), relative pressure level, and direction of flow. c) This included but was not limited to ANSI/IIAR 2 - 2021 Section 5.14.6, when the ammonia piping system line S HPR associated with HV2 located in Powerhouse Yard on P&ID R 706 was not labeled with the following information: "ammonia, physical state (e.g. liquid or gas), relative pressure level, and direction of flow. d) This included but was not limited to ANSI/IIAR 2 - 2021 Section 5.14.6, when the ammonia piping system line CD associated with EC6 located in Powerhouse Yard on P&ID R 707 was not labeled with the following information: "ammonia, physical state (e.g. liquid or gas), relative pressure level, and direction of flow. This hazardous condition exposed employees engaged in repairing, replacing, operating, inspecting, testing, and maintenance activities of covered process equipment to toxic, cryogenic, and fire hazards in the event of an anhydrous ammonia release.