Violation Detail
Standard Cited: 19260451 G01 General requirements.
Inspection Nr: 1568104.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,801.00
Current Penalty: $4,350.75
Issuance Date: 03/18/2022
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/06/2022
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 04/07/2022
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection | 
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/07/2022 | $4,350.75 | 04/06/2022 | Serious | |
| Penalty | Z: Issued | 03/18/2022 | $5,801.00 | 04/06/2022 | Serious | 
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(g)(1):Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section: (a) Dixey Land Energy at Customer Warehouse 902 Strasburg Pike Strasburg PA - The employer did not provide fall protection for the employee elevated 12 to 15 feet on an elevated surfaces of a skid, on or about December 10, 2021. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.