Violation Detail
Standard Cited: 19261051 A General requirements.
Inspection Nr: 1553522.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,188.00
Current Penalty: $11,188.00
Issuance Date: 03/14/2022
Nr Instances: 2
Nr Exposed: 4
Abatement Date: 04/07/2022
Gravity: 5
Report ID: 0420100
Contest Date: 04/13/2022
Final Order: 03/31/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/31/2023 | $11,188.00 | 04/07/2022 | Serious | |
Penalty | C: Contested | 04/26/2022 | $11,188.00 | 04/07/2022 | Serious | |
Penalty | Z: Issued | 03/14/2022 | $11,188.00 | 04/07/2022 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.1051(a): Stairway(s) or ladder(s) were not provided at all personnel points of access where there was a break in elevation of 19 inches (48 cm) or more, or no ramp, runway, sloped embankment, or personnel hoist was provided: a) On or before September 16, 2021 at the Bull Run Power Plant "Charlie" and "Delta" precipitator insulation project employees were exposed to fall hazards when accessing the top of the electrical insulator compartments at a height above the roof of 61 inches to perform work while on the compartment and the employer did not ensure a stairway or ladder was provided to all personnel points of access where there was a break in elevation of 19 inches or more.