Violation Detail
Standard Cited: 19100269 L03 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1546011.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,801.00
Current Penalty: $3,770.65
Issuance Date: 01/31/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 02/04/2022
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 03/04/2022
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/04/2022 | $3,770.65 | 02/04/2022 | Serious | |
| Penalty | Z: Issued | 01/31/2022 | $5,801.00 | 02/04/2022 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(l)(3)(iii):The employer did not ensure that no employee approached or took any conductive object closer to exposed energized parts than the employer's established minimum approach distance, unless provisions described in (l) (3) (iii) (A) - (C) were followed: On August 3,2021, the supervisor was exposed to electrical hazards while working with power lines.