Standard Cited: 19260150 A01 Fire protection.
This violation item has been deleted.
Inspection Nr: 1530769.015
Citation: 01002
Citation Type: Serious
Abatement Date: 12/06/2021 2
Initial Penalty: $10,513.00
Current Penalty: $0.00
Issuance Date: 11/08/2021
Nr Instances: 1
Nr Exposed: 7
Related Event Code (REC):
Gravity: 10
Report ID: 0317300
Contest Date:
Final Order: 12/08/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/08/2021 | $0.00 | 12/06/2021 | Serious | |
Penalty | Z: Issued | 11/08/2021 | $10,513.00 | 12/06/2021 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.150(a)(1): The employer did not develop and maintain a fire protection program to be followed throughout all phases of construction and demolition work, and did not provide for the firefighting equipment as specified in this subpart: a) The Hyatt House at 17254 Five Points Square Lewes, DE 19958: On or about May 13, 2021, the employer did not provide nor was the Foreman able to acknowledge there was a fire protection program on site where employees worked with flammable materials including but not limited to gasoline, wood, paper and ignition sources were present including but not limited to heat and spark producing equipment, compromised electrical components provide any type of fire protection program to ensure that proper fire protection was addressed and the employees knew what to do in the event of a fire. Furthermore, employee were working on the roof of the building with limited access through a hatch that exposed the employees to further hazards.