Violation Detail
Standard Cited: 19100147 C06 I C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1470791.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,145.00
Current Penalty: $7,000.00
Issuance Date: 04/13/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 05/05/2020
Gravity: 10
Report ID: 0213600
Contest Date:
Final Order: 05/05/2020
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/05/2020 | $7,000.00 | 05/05/2020 | Serious | |
Penalty | Z: Issued | 04/13/2020 | $12,145.00 | 05/05/2020 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i)(C): Where lockout was used for energy control, the periodic inspection did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected: a) On or about 03/19/2020 at the Collins plant; where employees were not evaluated/certified performing an actual machine lockout in the plant. Employees perform covered operations such as, but not limited to: cleaning the baghouse screw conveyor. ABATEMENT DOCUMENTATION REQUIRED