Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1463392.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $9,639.00
Current Penalty: $0.00
Issuance Date: 03/30/2020
Nr Instances: 3
Nr Exposed: 10
Abatement Date: 04/17/2020
Gravity:
Report ID: 0522300
Contest Date:
Final Order: 04/27/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/27/2020 | $0.00 | 04/17/2020 | Other | |
Penalty | Z: Issued | 03/30/2020 | $9,639.00 | 04/17/2020 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed. On or about February 12, 2020, the employer failed to conduct an audit of their control of hazardous energy program to ensure that the program procedures are up to date and effective. The last review of this program was conducted in 2018 and since that date, there have been new employees and systems put into service, to include adding locking out the hydraulic energy source on the presses. Presses to include but not limited to the Trumpf Press Brake (serial#50504A0465).