Violation Detail
Standard Cited: 19260451 B05 II General requirements.
Inspection Nr: 1458214.015
Citation: 01002
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $4,048.00
Current Penalty: $1,114.00
Issuance Date: 07/20/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0214700
Contest Date: 09/23/2020
Final Order: 03/18/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 03/18/2021 | $1,114.00 | Serious | ||
Penalty | C: Contested | 09/23/2020 | $4,048.00 | Serious | ||
Penalty | Z: Issued | 07/20/2020 | $4,048.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilivered end. a) Worksite, 57 Glenmore Ave, Montauk NY, West Side of Building - Employees were performing cedar shake siding installation work from a fabricated frame scaffold platform approximately 20-feet above the ground with a plank extended approximately 9-feet beyond the support; on or about 01/24/2020. Note: Because abatement of this violation is already documented in the case file, the employer need not submit certification or documentation of abatement for this violation as normally required by CFR 1903.19.