Violation Detail
Standard Cited: 19260034 A Means of egress.
Inspection Nr: 1454722.015
Citation: 01002
Citation Type: Other
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $5,397.00
Current Penalty: $4,317.00
Issuance Date: 03/26/2020
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 04/14/2020
Gravity:
Report ID: 0625700
Contest Date: 04/16/2020
Final Order: 06/12/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 06/26/2020 | $5,397.00 | 04/14/2020 | Serious | |
Penalty | R: Review Commission | 06/12/2020 | $4,317.00 | 04/14/2020 | Other | |
Penalty | Z: Issued | 03/26/2020 | $5,397.00 | 04/14/2020 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.34(a): Building or structure exits were not so arranged and maintained as to provide free and unobstructed egress from all parts of the building or structure at all times when it was occupied: On or about October 12, 2019, on floors seven through eighteen of the Hard Rock Hotel construction site at 1031 Canal St., New Orleans, LA, employees performed welding work where means of egress were not maintained as to allow free and unobstructed egress.