Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1396929.015
Citation: 01002
Citation Type: Serious
Abatement Date: 06/20/2019 2
Initial Penalty: $2,273.00
Current Penalty: $1,363.80
Issuance Date: 05/24/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0626300
Contest Date:
Final Order: 06/24/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/24/2019 | $1,363.80 | 06/20/2019 | Serious | |
Penalty | Z: Issued | 05/24/2019 | $2,273.00 | 06/20/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) (a) Employees at the site were exposed to fall hazards while mixing mortar from the 2nd level of the scaffold assemble which was not fully planked.