Violation Detail
Standard Cited: 19100107 B08 Spray finishing using flammable and combustible materials.
Inspection Nr: 1381747.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $7,577.00
Current Penalty: $4,546.20
Issuance Date: 05/09/2019
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0418800
Contest Date:
Final Order: 05/22/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/22/2019 | $4,546.20 | Serious | ||
Penalty | Z: Issued | 05/09/2019 | $7,577.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.107(b)(8): Each spray booths was not separated from other operations by not less than 3 feet, or by a greater distance, or by such partition or wall as to reduce the danger from juxtaposition of hazardous operations. On or about 2/28/2019, at the Axle Department of Man Engines & Components Inc., 591 SW 13th Terrace, Pompano Beach, FL 33069, a workstation was placed adjacent to a spray booth, exposing employees working in the area to a fire hazard.