Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1371253.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,934.00
Current Penalty: $7,160.40
Issuance Date: 06/03/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/19/2019
Gravity: 10
Report ID: 0214500
Contest Date:
Final Order: 07/19/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/19/2019 | $7,160.40 | 07/19/2019 | Serious | |
Penalty | Z: Issued | 06/03/2019 | $11,934.00 | 07/19/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: a) Production Area: The company did not have specific energy control procedural steps to the control of hazardous energy for equipment's such as but not limited to Repak RE 25 meat packaging machines, Forming machines and Grinders machines, on 1/14/2019.