Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1327120.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $7,760.40
Issuance Date: 10/18/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 12/12/2018
Gravity: 10
Report ID: 0522500
Contest Date:
Final Order: 11/08/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/08/2018 | $7,760.40 | 12/12/2018 | Serious | |
Penalty | Z: Issued | 10/18/2018 | $12,934.00 | 11/07/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed. a. On or about July 26, 2018, located in the foundry on the transfer conveyor, the employer did not ensure that periodic audits of the lockout/tagout procedures were adequately conducted for the mold transfer conveyor, thereby exposing the employees to the hazards associated with service and maintenance activities on the conveyor.