Violation Detail
Standard Cited: 19100147 F01 V The control of hazardous energy (lockout/tagout).
Inspection Nr: 1313616.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,174.00
Current Penalty: $3,104.00
Issuance Date: 10/24/2018
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 11/02/2018
Gravity: 10
Report ID: 0523900
Contest Date:
Final Order: 11/07/2018
Related Event Code (REC): A;R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/07/2018 | $3,104.00 | 11/02/2018 | Serious | |
Penalty | Z: Issued | 10/24/2018 | $5,174.00 | 11/02/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(f)(1)(v): All systems were not de-energized and energy control measures reapplied in accordance with paragraph (d) of this section to continue the servicing and/or maintenance: (a) Sawmill; On or about April 30, 2018, Lockout was not reapplied on the electrical disconnect for a debris blower fan system during trouble shooting operations. A hand injury occurred between the drive pulleys and belts of the blower fan.