Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1305564.015
Citation: 01002
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $2,217.00
Current Penalty: $1,330.20
Issuance Date: 06/04/2018
Nr Instances: 1
Nr Exposed: 7
Related Event Code (REC):
Gravity: 5
Report ID: 0418400
Contest Date:
Final Order: 07/24/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/24/2018 | $1,330.20 | Serious | ||
Penalty | Z: Issued | 06/04/2018 | $2,217.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights is no more than 1 inch (2.5 cm) wide: A) South side of building, on or about March 29, 2018, employees were working from the first and second tier of a two tier scaffold that were not fully planked, exposing the employees to a 6 foot and a 12 foot fall hazard.