Violation Detail
Standard Cited: 19261101 G03 III Asbestos
Inspection Nr: 1282589.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $10,163.00
Current Penalty: $3,000.00
Issuance Date: 02/22/2018
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 03/05/2018
Gravity: 5
Report ID: 0316100
Contest Date: 03/16/2018
Final Order: 07/29/2019
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/29/2019 | $3,000.00 | 03/05/2018 | Other | |
Penalty | C: Contested | 03/19/2018 | $10,163.00 | 03/05/2018 | Serious | |
Penalty | Z: Issued | 02/22/2018 | $10,163.00 | 03/05/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.1101(g)(3)(iii): Dust and debris containing asbestos containing material and presumed asbestos containing material were dry swept, shoveled or removed by other dry clean-up methods: (a) 3rd Floor Work Floor Buffer Area - On or about August 24, 2017, Labor Custodians and Mechanics used brooms to sweep up crumbled asbestos containing asphalt floor planks, a Class IV Asbestos activity and the material was in a dry state. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).