Violation Detail
Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1273624.015
Citation: 01002
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $12,675.00
Current Penalty: $12,675.00
Issuance Date: 04/20/2018
Nr Instances: 1
Nr Exposed: 100
Abatement Date:
Gravity:
Report ID: 0420600
Contest Date: 05/11/2018
Final Order: 04/22/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 04/22/2019 | $12,675.00 | Other | ||
Penalty | C: Contested | 05/16/2018 | $12,675.00 | Serious | ||
Penalty | Z: Issued | 04/20/2018 | $12,675.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures were not developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: a. On or about 10/26/2017, at the Big Bend power plant, employees were exposed to potential hazardous energies, in that, employees were allowed to use tools, such as hammers and impact wrenches in an effort to stop leaks on the Condenser #3 riser manway covers without developing and following a LOTO procedure to eliminate water pressure on the door.