Violation Detail
Standard Cited: 19260962 C
This violation item has been deleted.
Inspection Nr: 1258259.015
Citation: 01002
Citation Type: Serious
Abatement Date: 01/24/2018
Initial Penalty: $12,934.00
Current Penalty: $0.00
Issuance Date: 01/09/2018
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0523300
Contest Date: 02/02/2018
Final Order: 08/16/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/16/2018 | $0.00 | 01/24/2018 | Serious | |
Penalty | C: Contested | 02/06/2018 | $12,934.00 | 01/24/2018 | Serious | |
Penalty | Z: Issued | 01/09/2018 | $12,934.00 | 01/24/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.962(c): Temporary protective grounds were not placed at such locations and arranged in such a manner that the employer can demonstrate will prevent each employee from being exposed to hazardous differences in electric potential: On or about August 24, 2017, temporary protective grounds had not been placed and arranged in such a manner to prevent employee(s) from being exposed to hazardous differences in electrical potential posed by the 138 kV transmission lines running parallel to the de-energized 345 kV transmission lines.