Violation Detail
Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1245410.015
Citation: 01002
Citation Type: Serious
Abatement Date: 02/09/2018 2
Initial Penalty: $12,675.00
Current Penalty: $11,407.50
Issuance Date: 12/27/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0420600
Contest Date:
Final Order: 01/19/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/19/2018 | $11,407.50 | 02/09/2018 | Serious | |
Penalty | Z: Issued | 12/27/2017 | $12,675.00 | 01/31/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures were not developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: a) The employer did not develop, document, and implement procedures for clearing clogs in a slag tank, on or about June 29, 2017.