Standard Cited: 19100179 G01 V Overhead and gantry cranes.
Inspection Nr: 1234806.015
Citation: 01002
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $1,500.00
Issuance Date: 09/22/2017
Nr Instances: 2
Nr Exposed: 40
Abatement Date:
Gravity:
Report ID: 0523400
Contest Date: 10/17/2017
Final Order: 03/09/2018
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/09/2018 | $1,500.00 | Other | ||
| Penalty | C: Contested | 10/19/2017 | $0.00 | Serious | ||
| Penalty | Z: Issued | 09/22/2017 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.179(g)(1)(v): Pendant control box(es) were not clearly marked for identification of functions. (a) The pendant control box for the Cleveland Tramrail 5 Ton overhead crane in Bay three (3) was not clearly marked for identification of functions. (b) The pendant control box for the Cleveland Tramrail 5 Ton overhead crane in Bay two (2) was not clearly marked for identification of functions.