Violation Detail
Standard Cited: 19260961 C06
This violation item has been deleted.
Inspection Nr: 1216360.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 05/31/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/06/2017
Gravity: 10
Report ID: 0627500
Contest Date: 06/26/2017
Final Order: 08/24/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/24/2018 | $0.00 | 06/06/2017 | Serious | |
| Penalty | C: Contested | 06/26/2017 | $12,675.00 | 06/06/2017 | Serious | |
| Penalty | Z: Issued | 05/31/2017 | $12,675.00 | 06/06/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.961(c)(6): The employer did not verify that lines and equipment were deenergized by testing the lines and equipment to be worked with a device designed to detect voltage: Transformer distribution work site: On or about March 7, 2017; the employer did not test the lines and equipment to verify the absence of voltage before employees worked on transformers. This condition exposed the employees to electrical shock hazards.