Violation Detail
Standard Cited: 19260451 C03 General requirements.
Inspection Nr: 1210783.015
Citation: 01002
Citation Type: Serious
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $2,173.00
Current Penalty: $2,000.00
Issuance Date: 03/07/2017
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 03/31/2017
Gravity: 5
Report ID: 0316700
Contest Date: 03/30/2017
Final Order: 06/22/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 06/22/2017 | $2,000.00 | 03/31/2017 | Serious | |
| Penalty | C: Contested | 04/07/2017 | $2,173.00 | 03/31/2017 | Serious | |
| Penalty | Z: Issued | 03/07/2017 | $2,173.00 | 03/31/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(c)(3): Supported scaffold poles, legs, post, frames, and/or uprights were not plumb and braced to prevent swaying and displacement: (a) 3rd FLOOR, WEST END - Employees were installing roofing metal from a custom built supported scaffold, and six (6) of the six (6) uprights supporting the scaffold ranged from approximately 2 to 5 degrees out of plumb, thereby exposing the employees to possible fall hazards of approximately 11 feet to the ground below, on or about February 13, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.