Violation Detail
Standard Cited: 19260451 B05 I General requirements.
Inspection Nr: 1196284.015
Citation: 01002
Citation Type: Serious
Abatement Date: 06/08/2017 2
Initial Penalty: $12,675.00
Current Penalty: $10,775.00
Issuance Date: 06/02/2017
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0215000
Contest Date:
Final Order: 07/07/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/07/2017 | $10,775.00 | 06/08/2017 | Serious | |
Penalty | Z: Issued | 06/02/2017 | $12,675.00 | 06/08/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(b)(5)(i): The end of a platform 10 feet or less in length extended over its support more than 12 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees and/or materials without tipping, or has guardrails which block employee access to the cantilevered end Location: 325 Kent Avenue, Brooklyn, NY. 4th Floor Courtyard North Side of South Tower. a) The platform planks of the Dunlop 12000 mast climber scaffold were not secured and extended more than 12 inches over its support. An employee fell two stories when the cantilevered platform plank tipped. On or about 12/09/2016. b) The platform planks of the Dunlop 1200 mast climber scaffold were not secured and extended more than 12 inches over the support on the scaffold used by employees on or about 04/11/2017.