Standard Cited: 19100147 C07 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1184785.015
Citation: 01002
Citation Type: Serious
Abatement Date: 04/17/2019 2
Initial Penalty: $8,149.00
Current Penalty: $12,932.00
Issuance Date: 03/07/2017
Nr Instances: 1
Nr Exposed: 8
Related Event Code (REC): C
Gravity: 5
Report ID: 0521400
Contest Date: 03/17/2017
Final Order: 11/30/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/30/2018 | $12,932.00 | 04/17/2019 | Serious | |
Penalty | C: Contested | 03/21/2017 | $8,149.00 | 04/13/2017 | Serious | |
Penalty | Z: Issued | 03/07/2017 | $8,149.00 | 04/13/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(7)(i): The employer did not provide training to ensure that the purpose and function of the energy control program are understood by employees and that the knowledge and skills required for the safe application, usage, and removal of the energy controls are acquired by employees: MES department, MES 1, MES 2, MES 3 - on or about October 18, 2016, each authorized and/or affected employee did not receive adequate workplace-specific and job-specific hazardous energy control training to ensure competency prior to performing servicing tasks. Operators were regularly entering machining areas (danger zones) to perform energized equipment setup in the point-of-operation, inspections, adjustments, and to maintain housekeeping. Operators were exposed to unexpected machine start-up likely to result in serious injuries due to struck-by and caught in-between hazards. Alternative measure, such as, but not limited to relying on a stopped cycle and/or program to prevent unexpected start-up on energized machines did not ensure equivalent safety. Other safeguards were not provided to prevent operators' access and/or disable hazardous operations start-up prior to exposure. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d)