Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1177547.015
Citation: 01002
Citation Type: Serious
Abatement Date: 12/22/2016 2
Initial Penalty: $12,471.00
Current Penalty: $12,471.00
Issuance Date: 11/28/2016
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0418300
Contest Date:
Final Order: 12/28/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 11/28/2016 | $12,471.00 | 12/22/2016 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) On or about 09/15/2016 - Dato Department, Building #3, machinery such as, but not limited to, the Selco WNT 600 panel saw had not been evaluated to ensure the procedures were being utilized or up to date.