Violation Detail
Standard Cited: 19261101 H01 IV Asbestos
Inspection Nr: 1165103.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $8,329.00
Current Penalty: $8,329.00
Issuance Date: 11/08/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/03/2017
Gravity:
Report ID: 0521400
Contest Date: 12/06/2016
Final Order: 07/03/2017
Related Event Code (REC):
Emphasis:
Substance: 9020
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/03/2017 | $8,329.00 | 08/03/2017 | Other | |
Penalty | C: Contested | 12/12/2016 | $8,329.00 | 12/30/2016 | Serious | |
Penalty | Z: Issued | 11/08/2016 | $8,329.00 | 12/30/2016 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.1101(h)(1)(iv): Respirators were not used during all Class II and III asbestos jobs where the employer had not produced a negative-exposure assessment. On or about July 6, 2016, an employee working at the site of Exelon Power Plant located in Morris, IL was exposed to asbestos containing material while encapsulating piping containing thermal system insulation and the employer did not ensure respiratory protection had been worn when a negative-exposure assessment had not been conducted. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).