Violation Detail
Standard Cited: 19100023 C01 Ladders.
Inspection Nr: 1110296.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,600.00
Current Penalty: $3,500.00
Issuance Date: 02/24/2016
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/14/2016
Gravity: 5
Report ID: 0316100
Contest Date: 03/21/2016
Final Order: 08/04/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/04/2016 | $3,500.00 | 03/14/2016 | Serious | |
Penalty | C: Contested | 04/22/2016 | $6,600.00 | 03/14/2016 | Serious | |
Penalty | Z: Issued | 02/24/2016 | $6,600.00 | 03/14/2016 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.23(c)(1): Open-sided floors and/or platforms four feet or more above adjacent floor or ground level were not guarded with standard railings (or equivalent) and toe boards: a) On or about November 12, 2015; Laundry Department; employees would climb on top of the machinery during schedule clean-up (Blow-down) exposing them selves to a fall hazard of approximately 8 feet to ground level. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.