Violation Detail
Standard Cited: 19100023 C03 Ladders.
Inspection Nr: 1102514.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $4,500.00
Current Penalty: $3,500.00
Issuance Date: 04/28/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0317700
Contest Date: 05/18/2016
Final Order: 06/30/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/30/2017 | $3,500.00 | Serious | ||
Penalty | C: Contested | 05/23/2016 | $4,500.00 | Serious | ||
Penalty | Z: Issued | 04/28/2016 | $4,500.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.23(c)(3): Regardless of height, open-sided floors, walkways, platforms, or runways above or adjacent to dangerous equipment, pickling or galvanizing tanks, degreasing units, and similar hazards were not guarded with a standard railing and toe board: a) US GreenFiber, Production Line 2 (Reynolds), Reclaim Area: An employee stood on an elevated platform while performing product reclaim operations at the Stantco 1800E reclaim hopper and the employer did not ensure that the platform was guarded on all sides with a standard railing, as discovered on or about 12/09/2016. ABATED DURING INSPECTION NO ABATEMENT CERTIFICATION REQUIRED