Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1082421.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,900.00
Current Penalty: $3,000.00
Issuance Date: 02/04/2016
Nr Instances: 10
Nr Exposed: 45
Abatement Date: 03/26/2016
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 02/25/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/25/2016 | $3,000.00 | 03/26/2016 | Serious | |
Penalty | Z: Issued | 02/04/2016 | $4,900.00 | 03/18/2016 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.119(d)(3)(i)(B): Information pertaining to equipment in the process did not include piping and instrument diagrams (P&IDs): a) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when piping specifications were not shown for ethyl chloride storage tank T-153 on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. b) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when hand valve A1-CH-002, a bleed line and valve between A1-CV-NIT and A1-HV-NIT and a flex line between WT-HV-NIT and WT-100 were not shown on on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. c) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when valves NIT-HV-004 and NIT-HV-005 were not shown to be normally padlocked on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. d) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when valves 153-HV-002 and WT-HV-SV were not shown to be normally padlocked or car sealed open on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. e) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when compressed air to pneumatic valves WT-CV-VENT, WT-CF-NIT, A1-CV-ETC, A1-CV-NIT and A1-CV-VA were not shown on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. f) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when design temperature and pressure ratings, size or capacity for tank T-153, tank WT-100 and autoclave A1 were not shown on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. g) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when failure modes of automatic valves were not shown on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. h) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when flash arresters on tanks T-153 and WT-100, a pressure relief valve upstream of NIT-HV-001, scales on tank WT-100 and autoclave A1 and an agitator on A1 were not labeled on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. i) Establishment - PEEB Process The employer did not ensure that the written process safety information included all necessary information pertaining to equipment in the process when blackening of certain hand valves including but not limited to 153-HV-DRN and WT-HV-SV was not explained on PEEB Process P&ID TCPA Rev. Dated 6 11/01/2014. Violations occurred on or about 8/10/15.