Standard Cited: 5A0001 OSH Act General Duty Paragraph

Inspection Nr: 106387822

Citation: 01002

Citation Type: Serious

Abatement Status: X

Initial Penalty: $5,000.00

Current Penalty: $258.00

Issuance Date: 03/31/1992

Nr Instances: 1

Nr Exposed: 19

Abatement Date: 03/31/1992

Gravity: 10

Report ID: 0420600

Contest Date: 04/24/1992

Final Order: 02/25/1993

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 02/25/1993 $258.00 03/31/1992 Serious  
Penalty Z: Issued 03/31/1992 $5,000.00 03/31/1992 Serious  

Text For Citation: 01 Item/Group: 002 Hazard: EXPLOSION

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the hazard of over presssurizing steam turbines leading to explosion of the casings or components: (a) Sulfuric Acid Plant, between the Cooling Basin and the Cooling Tower, two steam turbines used to run the "BJ" pumps did not have a full flow relief valve installed in the exhaust line between the turbine casing and the first shut off valve, on or about 10/8/91. Among other methods, one feasible and acceptable abatement method to correct this hazard is to install full flow relief valves on all steam turbines. (b) Sulfuric Acid Plant, steam boiler water feed pump, the sentinel relief valve was removed from the turbine and not replaced, on or about 10/22/91. Among other methods, one feasible and acceptable abatement method to correct this hazard is to install sentinel relief on all steam turbines. (c) Sulfuric Acid Plant, preventive maintenance and testing was not conducted to ensure that the sentinel relief valves on steam turbines were functioning properly, on or about 10/8/91. Among other methods, one feasible and acceptable abatement method to correct this hazard is to develop inspection procedures for maintenance of the sentinel relief valves, according to the steam turbine manufacturers operating manuals.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.