Violation Detail
Standard Cited: 19100212 A03 II General requirements for all machines.
Inspection Nr: 1051971.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,500.00
Current Penalty: $2,730.00
Issuance Date: 06/24/2015
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 09/30/2015
Gravity: 5
Report ID: 0522300
Contest Date:
Final Order: 07/14/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/14/2015 | $2,730.00 | 09/30/2015 | Serious | |
| Penalty | Z: Issued | 06/24/2015 | $3,500.00 | 07/14/2015 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.212(a)(3)(ii): Point of operation guards were not designed and constructed as to prevent the operator from having any part of their body in the danger zone during the operating cycle: The hydraulic bar straightener located in the welding department had unguarded pinch points between the bar and the anvils, which supported the bar, and between the bar and the ram.