Violation Detail
Standard Cited: 19100219 B01 Mechanical power-transmission apparatus.
Inspection Nr: 1713540.015
Citation: 01001K
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,687.00
Current Penalty: $0.00
Issuance Date: 05/14/2024
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 03/03/2025
Gravity: 5
Report ID: 0316700
Contest Date: 06/14/2024
Final Order: 02/10/2025
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/10/2025 | $0.00 | 03/03/2025 | Serious | |
Penalty | C: Contested | 07/08/2024 | $3,687.00 | 06/10/2024 | Serious | |
Penalty | Z: Issued | 05/14/2024 | $3,687.00 | 06/10/2024 | Serious |
Text For Citation: 01 Item/Group: 001K Hazard:
29 CFR 1910.219(b)(1): Flywheels with parts seven feet or less above floors or platforms were not guarded in accordance with the requirements specified in 29 CFR 1910.219(b)(1)(i) through (b)(1)(iv): (a) Fabrication Area - The flywheel, with a bottom height of 6 feet 8 inches above the floor, on the 125-ton Federal Press No. 10 part-revolution mechanical power press did not have guarding on the inner and outer sides of the lower portion of the flywheel less than 7 feet above the floor, exposing employees to the hazard of getting caught-in rotating parts, on or about November 30, 2023. (b) Fabrication Area - The flywheel, with a bottom height of 59 inches above the floor, on the 90-ton Bliss 21 B mechanical power press, did not have complete guarding in that the employer did not have both halves of the existing guard tighten together, leaving a few-inch wide separation, which extended from the bottom periphery to the top periphery of the guard, exposing employees to the hazard of getting caught-in rotating parts, on or about November 30, 2023. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and state employees and their representatives were informed of this abatement.