Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1584397.015
Citation: 01001D
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,801.00
Current Penalty: $0.00
Issuance Date: 08/09/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 10/03/2022
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 08/23/2022
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/23/2022 | $0.00 | 10/03/2022 | Serious | |
| Penalty | Z: Issued | 08/09/2022 | $5,801.00 | 09/02/2022 | Serious |
Text For Citation: 01 Item/Group: 001D Hazard:
29 CFR 1910.147(c)(6)(i):The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed. (A) The periodic inspection shall be performed by an authorized employee other than the ones(s) utilizing the energy control procedure being inspected. (B) The periodic inspection shall be conducted to correct any deviations or inadequacies identified. (C) Where lockout is used for energy control, the periodic inspection shall include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected. a) On or about March 17, 2022, the employer did not conduct a periodic inspection of the lockout procedures for equipment such as but not limited to the Cincinnati Press Brakes #2, 3, 4, 5, and 6.