Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1793264.015
Citation: 01001C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/28/2025
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 08/06/2025
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order: 06/24/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/24/2025 | $0.00 | 08/06/2025 | Serious | |
Penalty | Z: Issued | 05/28/2025 | $0.00 | 06/16/2025 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed. On or about December 2, 2024, and at times prior thereto, within the rubber milling production area, employees used the Thropp Rubber Mill and the energy control procedure was not periodically inspected.