Violation Detail
Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1767969.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/03/2025
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 03/04/2025
Gravity: 10
Report ID: 0830600
Contest Date:
Final Order: 02/27/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 02/03/2025 | $0.00 | 03/04/2025 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(d)(6): Prior to starting work on machines or equipment that had been locked out or tagged out, the authorized employee did not verify that isolation and de-energization of the machine or equipment had been accomplished: (a) Rail Mill, North stamp wheel: On or about August 9, 2024 , and at times prior, employees replacing a retaining pin on the North stamp wheel did not verify that the sled had been isolated and deenergized. This condition exposed employees to caught-between and crushed-by hazards resulting in a fatality.