Violation Detail
Standard Cited: 19260451 F03 General requirements.
Inspection Nr: 1706401.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Not Completed - AD Discretion
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/16/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/13/2024
Gravity: 10
Report ID: 0112300
Contest Date: 03/13/2024
Final Order: 04/29/2024
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/29/2024 | $0.00 | 03/13/2024 | Serious | |
Penalty | C: Contested | 03/13/2024 | $0.00 | 03/13/2024 | Serious | |
Penalty | Z: Issued | 02/16/2024 | $0.00 | 03/13/2024 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1926.451(f)(3): Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity: a) Facility: 129 Morton Ave. Woonsocket, RI: On or about 10/25/2023, the employer did not ensure that the Skyjack scissor lift was inspected by a competent person before each work shift. Employees were removing roofing materials at a height of approximately fourteen feet (14') and the mid-rail chain was not in use.