Violation Detail
Standard Cited: 19100244 A02 III Other portable tools and equipment.
Inspection Nr: 1651898.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $15,625.00
Current Penalty: $0.00
Issuance Date: 04/17/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 05/11/2023
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 05/10/2023
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/10/2023 | $0.00 | 05/11/2023 | Serious | |
Penalty | Z: Issued | 04/17/2023 | $15,625.00 | 05/11/2023 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.244(a)(2)(iii): After the load has been raised, it shall be cribbed, blocked, or otherwise secured at once. a) On February 21, 2023, the employer did not ensure that after the New Holland Hayliner 275 Plus, weighing approximately 3,940 pounds, was raised that it was secured by being cribbed and blocked to prevent exposure to any collapse before an employee worked under the load.