Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1646771.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/31/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 06/29/2023
Gravity: 10
Report ID: 0523900
Contest Date: 06/27/2023
Final Order: 12/08/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/08/2023 | $0.00 | 06/29/2023 | Serious | |
| Penalty | C: Contested | 06/27/2023 | $0.00 | 06/29/2023 | Serious | |
| Penalty | Z: Issued | 05/31/2023 | $0.00 | 06/29/2023 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): (a) Plant 2 sub-finishing department, glue roller press; On or about January 23, 2023 and on dates prior, the 2D320 Press Roller was not isolated from the electrical energy source during setup and cleaning activities, in that the main power cord was not unplugged.
Translate