Violation Detail
Standard Cited: 19100176 B Handling materials - general.
This violation item has been deleted.
Inspection Nr: 1587570.015
Citation: 01001C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/18/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 05/31/2022
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 06/09/2022
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/09/2022 | $0.00 | 05/31/2022 | Serious | |
| Penalty | Z: Issued | 05/18/2022 | $0.00 | 05/31/2022 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.176(b): Storage of material created a hazard: a) Ellwood City Forge Company, Machine shop lay down area/Mezzanine area, on or about April 4th, 2022 and times prior thereto: The storage of material created a struck-by hazard in the Machine shop mezzanine area in that, a round bar was stored too close to steel blocks that were being loaded/unloaded in the area with the Zenar brand crane (Serial #8607). An employee sustained a left leg fracture when a round bar was struck during the unloading process of a steel block in the mezzanine area. The round bar rolled onto the employees left leg during the incident. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Translate