Violation Detail
Standard Cited: 19100147 F01 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1395322.015
Citation: 01001C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,210.00
Current Penalty: $0.00
Issuance Date: 07/08/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 08/05/2019
Gravity: 10
Report ID: 0521100
Contest Date:
Final Order: 07/23/2019
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/23/2019 | $0.00 | 08/05/2019 | Serious | |
| Penalty | Z: Issued | 07/08/2019 | $10,210.00 | 08/05/2019 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(f)(1): Testing or positioning of machines, equipment or components thereof. In situations in which lockout or tagout devices must be temporarily removed from the energy isolating device and the machine or equipment energized to test or position the machine, equipment or component thereof, the following sequence of actions shall be followed as outlined in 29 CFR 1910.147(f)(1)(i)-(v): On or about April 19, 2019, employee(s) the repositioning of the hydraulic ram of the Balemaster (Model: 44750-10, G, J, 4, Q, T, U, X, Z, 7,Z, 9; S/N: B0122-04-13389583) and did not ensure all employees were removed from the equipment exposing employees to caught in and struck by hazards.