Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1350804.015
Citation: 01001C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/04/2019
Nr Instances: 1
Nr Exposed: 8
Abatement Date: 02/22/2019
Gravity: 5
Report ID: 1032500
Contest Date: 02/01/2019
Final Order: 05/08/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/08/2019 | $0.00 | 02/22/2019 | Serious | |
Penalty | C: Contested | 02/04/2019 | $0.00 | 02/22/2019 | Serious | |
Penalty | Z: Issued | 01/04/2019 | $0.00 | 02/22/2019 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1910.147(c)(6)(ii): The employer did not certify that periodic inspections of the energy control procedures had been performed: a) Facility: On October 2, 2018 and at times prior thereto a the employer had not certified that an annual or periodic review of the energy control program for the Dixie Road picker was conducted. The energy control program used by the employer was a draft, with an effective date of March 2015, and a revised date of December 2016. Note) Certification of corrective action is required for this item.